TGE are pleased to inform you about the good news regarding our 240,000 m3 Propane Storage Tanks Extension Project for SP Chemicals (TAIXING) Co., Ltd.

The air-raising of the steel roofs for the two 120,000m³ cryogenic storage tanks have been successfully achieved on 16.09.2022 and 18.08.2022

The roof air-raising progress took about 150 minutes, after which the roof with approx. 720 tons of steel reached its final position and then had been fixed in the next hours by welding.

TGE would like to thank all the parties and personnel involved in this project.

Special thanks to the project team on site for their hard works to ensure this important project milestones.

The construction of two 120,000m³ propane tanks of steel/concrete full-containment design is an extension project of TGEs recent 05491 project, which consisted of one 120,000 m³ full containment tank  for propane and two 120,000 m³ full containment tanks, designed for multi-product of #propane and #ethane.

During the earlier time, TGE had also delivered a 30,000 m³ steel/steel storage tank and one 20,000 m³ steel/steel tank for the storage of #ethylene to the same client.

TGE would like to use this opportunity to thank their client SP Chemicals (TAIXING) Co., Ltd. for the continuous cooperation and their trust placed in TGE.

For more information visit tge-gas.com

21st September 2022