The U.S. Federal Energy Regulatory Commission (FERC) has issued Notice of Schedule for Environmental Review to Commonwealth LNG for the construction of one LNG plant, including six gas liquefaction trains and appurtenant facilities. Each train will have a liquefaction design capacity of approximately 1.4 million metric tonnes per annum (Mtpa) for a total nominal liquefaction capacity of 8.4 Mtpa.

Located on the west side of the Calcasieu Ship Channel, near the entrance to the Gulf of Mexico, the project will include six LNG storage tanks each with a capacity of 40,000 cbm, one marine loading berth capable of loading LNG carriers up to a capacity of 216,000 cbm, and a 3.04-mile long, 30-inch diameter pipeline that will connect the LNG Facility with existing intrastate and interstate pipelines for the purpose of supplying gas to the project.

FERC will issue the draft EIS in May 2020 and the issuance of Notice of Availability of the final EIS will take place on October 2, 2020. The 90-day Federal Authorization Decision Deadline will take place on December 31, 2020

“We are very pleased to receive FERC’s Issuance of Notice of Schedule for Environmental Review. It confirms that our project remains on schedule to take FID in Q1 2021 and start commercial operations in Q1 2024,” said Paul Varello, Commonwealth LNG’s President and CEO.

For more information visit www.commonwealthlng.com