12.07.2016. Enable Midstream’s Bradley II Plant is now fully operational, the partnership has announced.
The Bradley II Plant, a 200 million cb ft per day (MMcf/d) natural gas processing plant located at Enable’s Bradley Processing Complex in Grady County, Oklahoma, strengthens Enable’s natural gas gathering and processing capabilities in the SCOOP and STACK plays in central Oklahoma.
“The Bradley II Plant provides capacity to support our customers’ development in the prolific SCOOP and STACK plays and continues the build out of our super-header system, which is positioned to support long term production growth out of these plays as well as other plays located in the Anadarko Basin,” said president and CEO Rod Sailor. “Bradley II will also provide natural gas supply into Enable’s interstate and intrastate transportation pipelines for delivery to downstream markets in the midcontinent and southeast United States.”
The plant is a cryogenic processing plant and is the ninth to be connected to Enable’s super-header processing system, a large-diameter pipeline network with the capacity to process almost 1.7 billion cb ft per day (Bcf/d) of natural gas.

12th July 2016