Elite Integrity Services said it is “rising up to the challenge” with its new client. It said: “When our client required three 30,000 bbl tanks to be constructed on a compressed schedule, our teams came together to make it happen!”

Working with all operators across the project, it developed a revolving schedule “to accommodate continuous construction and mitigate schedule loss with the challenging climate conditions”. These included severe winter conditions and freezing temperatures.

Project Highlights:

• 24” diameter, coated large internal piping assemblies
• Great communication with client and EPC to expedite project approval processes
• Four months to complete the tanks including the installation of Sandborn Internal Floating Roofs
• Challenging winter conditions

For more information visit www.eliteintegrityservices.com

2nd July 2020